Three more weekend closures planned for Blackwall Tunnel
TRANSPORT bosses will need three more weekend closures to complete their restoration project at the Blackwall Tunnel.
The project is due to be completed by December this year – several months ahead of the date originally predicted.
The final closures are needed for upgrade works on the 1.4km tunnel that cannot be completed when traffic is flowing through.
It will shut southbound on the Easter Bank Holiday weekend and the weekends of June 10-13 and August 12-15.
Garrett Emmerson, Chief Operating Officer for London Streets for TfL, said: “Although these works are progressing even better than we had hoped, there will be additional congestion due to these weekend closures.
You may also want to watch:
“We therefore ask people to plan their journeys for these weekends in advance and avoid travelling through the area if at all possible.”
During the weekend closures, the Rotherhithe Tunnel will again operate two lanes in the southbound direction only, while the Blackwall Tunnel will carry only northbound traffic. Drivers will also be able to use alternative river crossings such as Tower Bridge, the Woolwich Ferry or the Dartford Crossing to complete their journey.
Most Read
- 1 Murder arrest after woman stabbed to death in Whitechapel this morning
- 2 Fury as family homes vanish when Isle of Dogs landlord converts to bedsits
- 3 Man sentenced after teenage boy groomed on Snapchat to sell heroin
- 4 Lovely Day for Aldgate School picked to sing on Billy Ocean's new single
- 5 Police e-fit expert retiring after 15 years at Bethnal Green
- 6 Leyton Orient announce partnership with Hartford Athletic
- 7 Two men arrested after police officers assaulted in Limehouse rave
- 8 Covid vaccination hub opening in Westfield next week
- 9 Teenager found dead in Victoria Park
- 10 Police hunt after stabbing in Cable Street: One man hurt
Work costing �70 million started in February 2010 and saw a series of weekend closures last year.
New ventilation shafts are now installed in the tunnel’s four shafts, with upgraded CCTV and new communications systems throughout.
There are now 26 inlets in the tunnel wall, fitted with emergency phones and a fire extinguisher for any vehicles that have broken down.